Casper Construction Progress Part 2 – 2024 – April through June
20 April 2024
On the 30th of March I went to Sheridan WY to check out the local club and pick up a couple of BLI Blueline Mikados from one of the guys there. He couldn't use them and offered me a great deal on them. I've got one of them running well, but the sound board in the second one appears to be fried. I bought a TCS decoder to install in it. The first one, number 362, is on the layout. The other one will be added after I get the new decoder in it. Both will be relettered for the Burlington.
On April 3rd I posted my latest layout update video:
Here's a closer view of the yard throat taken the next day. Since all this trackage is hidden, I don't need to add ties under the turnouts, but the rails still need to be supported. I kept all the frames from the Fast Tracks tie strips I used to use, so I simply cut those frames to fit under the rails. I also started adding the first sections of flextrack.
By the 16th all the flextrack was laid on this section. It doesn't reach the end of the roadbed because there will be Atlas rerailers on each track at each section break. That will make it easy to assemble the sections together as I install them under Casper.
All the yard tracks are Atlas code 100 flextrack, which used to be on my behemoth helix on version 2 of the layout in New Jersey, over 15 years ago. Some of it will finally be reused.
On the 17th I started wiring. First I installed all the barrier strips for the electrical connections. From left to right we have the strip for the Tortoise switch machines, then the small strip for track feeders, then the power strip for the occupancy detectors - old IRDOTs from MicroMark (no longer available), that also came off the version 2 layout, and finally the LED signal output strips from the IRDOTs.
And when I was done it looked like this. I'll be able to add the Burlington logo without a problem at this point. The slightly dulled area where I removed the old logo will disappear when the locomotive is weathered. This worked a lot better than I thought it would. I was afraid I would have to repaint the entire tender.
Once the pieces were loose again I turned the first section up on it's side to wire the Tortoises and IRDOTs (the wire I was waiting for arrived today). Here the IRDOTs are wired. Tortoises will be done probably tomorrow, then I'll add track feeders to the second section. That's the only wiring needed for that section. The third section will also have IRDOTs, at about the mid-point of each yard track.
15 May 2024
At this point a big problem showed up. When I was planning out the east staging lead elevations, I neglected to take into account the depth of the benchwork under Thermopolis and Wind River Canyon. When I placed my six foot level between the end of the curves under Holly Sugar over to the Thermopolis benchwork, it turned out the line would run smack into the benchwork! The bottom of the level is the height the subroadbed needed to be to provide a decent grade on the line.
Back to the east staging lead, fortunately a bit of re-planning based on a suggestion from Dave provided the solution to running into the benchwork. Rather than take east staging from Greybull, it would now run down the Cody Branch Helix and take off from the branch at the east entrance to Powell. No ideal, but it was the only option. So May 1st I began cutting in a new turnout at the east end of Powell.
A bit further down the line I had to trim some risers and change a few supports here and there, but it wasn't overly difficult. Here I've added a new support for the Cody Branch off a Basin riser, and am preparing to remove the old Cody Branch riser. The new east staging subroadbed is sitting cock-eyed on top of the benchwork joists below.
On May 3rd I uploaded layout update #54 to YouTube.
By the time Dave left for home, all sections of the yard were connected together and the entire thing was in place ready for raising into it's final location. We didn't have time to do that before he left, and we were too exhausted to do it anyway. I have a few ideas about how to lift the entire thing into place, and will be working on that over the next few days.
28 May 2024
On the 21st I hooked up my DCC system to the yard temporarily and ran a loco all the way down and back on every track.
On the 22nd I began adding the cabling that will run to the control panel. Here I've just finished adding the 12-conductor cable that will provide the occupancy indications for the west set of IRDOTs.
On the 24th I wired the center set of IRDOTs. I stopped there because the east end will be easily accessible even after the yard is raised to final position.
Speaking of raising the yard, I began setting up for that on the 24th. The east end of the yard sticks out a bit beyond the Powder River benchwork, so I can use threaded rods there. I'll have legs at that end. Meanwhile, I'm using automotive jack stands on stools to support the yard as I hoist it up.
The last couple of days I've spent many hours on the creeper rolling back and forth, slowly raising the yard to within about two inches of its final elevation. I've tied the west lead back into the subroadbed parallel to the wall between Casper and Douglas, but track isn't connected there yet.
At my age it isn't particularly easy to work from a creeper. Heck, it's pretty difficult even getting onto and off of the creeper! But I'm getting it done. I'll add the lead to the east end of the yard before raising it up any more. That will take a day or two, then it's back to raising the yard and making final adjustments.
12 June 2024
Over the next week I did just a couple of small tasks on the staging yard project: installing the last short bit of track on the west staging lead; cleaning all the track; etc.
Mostly I worked on the control panel for the yard. I dug out the old staging panel from Version 2 of the layout and traced some of the power circuitry I'd used back then - about 20 years ago. Then I began working on the new panel graphics. After a couple of false starts I remembered how I'd crated the old panel face, and set about creating the new one. By June 7th I had it pretty much complete:
On June 3rd I posted my latest layout update video:
Yesterday (the 11th) Dave came down from Basin and we spent the day making final adjustments to the staging yard elevation, and flattening the whole thing out. Here. after getting the entire yard within about a 16th of an inch of final elevation, I've attached the first permanent leg to the east end of the yard.
Once adjustments on the yard were completed and the remaining legs installed on the east end, we set the grade on the east lead all the way back to Holly Sugar. Here Dave is adjusting one of the supports under Wind River Canyon. I still have to glue the subroadbed to the supports and attach the supports to the "risers" (descenders?). Right now all the supports are simply clamped to the risers.
Finally it was time to run a test train! After sending a loco with one car down the east lead from Powell all the way across the yard to the west lead, We grabbed a proper train (one of the reefer express trains waiting on the west staging lead) and ran it all the way from Greybull through the longest staging yard track and out to the end of the east lead at Powell. Here the train has crossed through the entire staging yard and is approaching the east lead.
Here's an overall view of the entire staging yard, taken this morning.
Next steps are to add the ground throw to the switch a Powell (I'll do that today), then final install all the supports for east and west staging (both ends are simply clamped in place right now). Then the final big project will commence - building and connecting up the control panel.